Contracts Process
Purpose: This document outlines the requirements and responsibilities for requesting and processing a new contract.
This regular contract process applies to all contracts that are not on UCR-approved standard templates. They must first go through the full review process meeting in the following order:
- Contracting
- Compliance
- Legal
- Sub-Business Owner
- Senior Leadership
- External
Contracts that are drafted on UCR-approved standard templates may go through the expedited process.
Note: this process is not for new contracts on a standard template. See Expedited Contracts Process for details.
-
Start Contract Process
- Requester enters complete contract request and upload all required documents into UCR SOM Cobblestone. Med school login credentials are required for access to the form.
- If complete information is not supplied, Contracts Office will return the request to the requester with a list of required information.
-
Review Process
Contracts Office
- Contracts office receives a contract request.
- If request is incomplete, contracts office to return application with list of required information.
- If request is complete, contracts office to create redline draft.
Redline Draft 1
- Send redline draft of the contract/amendment along with the contract review form (CRF) to the compliance office for review and approval, with cc to the FAO. (mandatory)
Compliance Office Review
- Compliance office reviews the contract and/or amendment. (mandatory)
- Compliance completes, signs, and returns CRF to the contracts office.
Legal Review
- Contract office sends the contract and/or amendment along with the CRF to legal for review and approval, with cc to the FAO and compliance. (mandatory)
- Legal completes, signs, and returns CRF to contracts office.
Sub-Business Owner Review (SBO Review)
- The contract and/or amendment along with the CRF is sent to sub-business owner for review. (mandatory)
- Business owner completes, signs, and returns CRF to contracts office.
Redline Draft 2
- Contracts office reviews and redlines the contract and/or amendment (Draft redline 2).
- Send to CEO, CFAO, and Office of Risk Management (if necessary).
Senior Leader Review
- CEO and CFAO completes, signs, and returns CRF to contracts office. (mandatory)
- Contracts office reviews and redlines the contract and/or amendment (Draft redline 3).
Redline Draft 3
- Contracts office reviews and redlines the contract and/or amendment (Draft redline 3).
- Send to affiliate for external review. (mandatory)
-
Approval Process
Approval
Not Approved - Redline after External Review
- If not approved, review and update with sub-business owner and applicable approvers.
Approved
- If approved, prepare final document and send to external party for execution. (mandatory).
External Signatures
- Route for authorized signatures (mandatory).
Internal Signatures
- Authorized approver reviews and signs, then returns to contract office. (NDAs only can be signed by the CEO. All other contracts must be signed by the dean.)
- Request completion of contract summary from FAO.
- Complete contract summary and return to contracts office.
-
Active
Active
Send notification email with:
- Copy of completed contract.
- Contract summary form.
- Send final executed copy to affiliate.